Consolidating the Computing Foundation, Ensuring Secure Operation|ZDATA's Mingwei 110kV No.2 Substation in Zhangjiakou and Ulanqab 110kV Yaxin Yunlian Substation Officially Commence Operation
Recently, the Mingwei 110kV No.2 Substation and the Ulanqab 110kV Yaxin Yunlian Substation have successively completed power transmission. During project construction, the design principles of high reliability, green energy efficiency, adaptability, and intelligent integration were strictly adhered to, providing reliable assurance for stable power supply.
Dual Hubs Successively Commence Operation, Computing Base Upgraded
► The Mingwei 110kV No.2 Substation commenced construction in early October 2024. During construction, ZDATA organized construction teams to overcome external challenges such as right-of-way acquisition delays and winter construction constraints. It achieved dual-circuit power transmission ahead of schedule on June 25, 2025, providing robust support for the power supply of ZDATA's Yu County project cluster.

► The Ulanqab 110kV Yaxin Yunlian Substation, located in the heart of the Chahar High-Tech Zone, faced complex land acquisition and construction bottlenecks. The project team proactively collaborated with relevant departments of Ulanqab Power Supply Company to overcome grid access restrictions during critical security periods for the national college entrance exams. By establishing a "night construction window" and "green approval channel," they completed the full line connection on schedule. The entire line passed acceptance on June 30, ensuring the substation achieved its power transmission target on July 1.

Racing Against Time, Experiencing ZDATA's "Acceleration"
► The successive commissioning of the Mingwei 110kV No.2 Substation and the Ulanqab 110kV Yaxin Yunlian Substation will provide stable, high-capacity power support for the massive regional data center clusters. This will underpin their massive data computing and storage tasks, facilitate interconnectivity in regions like Beijing-Tianjin-Hebei and Ulanqab, and deliver solid energy support for regional digital economic development.

Recommended News
-
02/142022
Building the National Computing Hub for "East Numbers and West Calculations" - ZDATA's Proposal at the Datong Municipal CPPCC's First Session
On the morning of February 10th, the first session of the 15th Datong Municipal Committee of the Chinese People's Political Consultative Conference (CPPCC) was grandly opened. The conference aimed to "take Xi Jinping Thought on Socialism with Chinese Characteristics for a New Era as a guide, comprehensively promote high-quality development, and gather mighty forces for 'striving for two five-year plans to enter the forefront!'". It fully leveraged the role of the specialized consultative body, allowing CPPCC members from various sectors and industries in the city, who shoulder the heavy trust and expectations of the people, to contribute to the economic, social, and democratic political development of Datong by offering advice and building consensus. -
01/072025
Breaking | ZDATA's "Titan Tower" Wins Prestigious "Cloud Computing Center Technology Award"
Recently, the 2024 Cloud Computing Center Technology Award results were announced. The "Titan Tower" data center project, jointly submitted by ZDATA Cloud Port Data Technology Co., Ltd. (a ZDATA subsidiary) and Beijing Volcano Engine Technology Co., Ltd., stood out for its groundbreaking achievements in extreme cooling efficiency and ultra-low-cost modeling. The project was honored with the 2024 Cloud Computing Center Technology Award - Excellence Award (Engineering Construction Category), marking a significant milestone in innovative data center solutions.