Consolidating the Computing Foundation, Ensuring Secure Operation|ZDATA's Mingwei 110kV No.2 Substation in Zhangjiakou and Ulanqab 110kV Yaxin Yunlian Substation Officially Commence Operation
Recently, the Mingwei 110kV No.2 Substation and the Ulanqab 110kV Yaxin Yunlian Substation have successively completed power transmission. During project construction, the design principles of high reliability, green energy efficiency, adaptability, and intelligent integration were strictly adhered to, providing reliable assurance for stable power supply.
Dual Hubs Successively Commence Operation, Computing Base Upgraded
► The Mingwei 110kV No.2 Substation commenced construction in early October 2024. During construction, ZDATA organized construction teams to overcome external challenges such as right-of-way acquisition delays and winter construction constraints. It achieved dual-circuit power transmission ahead of schedule on June 25, 2025, providing robust support for the power supply of ZDATA's Yu County project cluster.
► The Ulanqab 110kV Yaxin Yunlian Substation, located in the heart of the Chahar High-Tech Zone, faced complex land acquisition and construction bottlenecks. The project team proactively collaborated with relevant departments of Ulanqab Power Supply Company to overcome grid access restrictions during critical security periods for the national college entrance exams. By establishing a "night construction window" and "green approval channel," they completed the full line connection on schedule. The entire line passed acceptance on June 30, ensuring the substation achieved its power transmission target on July 1.
Racing Against Time, Experiencing ZDATA's "Acceleration"
► The successive commissioning of the Mingwei 110kV No.2 Substation and the Ulanqab 110kV Yaxin Yunlian Substation will provide stable, high-capacity power support for the massive regional data center clusters. This will underpin their massive data computing and storage tasks, facilitate interconnectivity in regions like Beijing-Tianjin-Hebei and Ulanqab, and deliver solid energy support for regional digital economic development.
Recommended News
-
08/202024
ZDATA drops another son, adds new projects to Ulaanbaatar's arithmetic map
-
03/042022
ZDATA Tops Beijing's "Specialized, Special, New" "Little Giant" Enterprise List
Recently, the Beijing Municipal Bureau of Economy and Information Technology issued a notice on the announcement of the second batch of "Little Giants" enterprise list in Beijing for the year 2021. ZDATA proudly made it to the list, marking another honor for the company after being recognized as a "specialized, refined, distinctive, and innovative" small and medium-sized enterprise in Beijing.